Pump Management Projects
|
As a division of Boulting Group, Pump Management has a complete in-house facility to provide turnkey pump projects. If the client requires any pump package, whatever the size, whatever the industry, Pump Management will provide a quality installation, with all the equipment selected on Pump Management’s values of:-
- Meeting industry and client specifications
- Superior engineered solutions
- Reliability
- Minimum maintenance
- Minimum life cycle cost
- Optimum energy efficiency
Pump Management has confidence in the quality of its installations. It provides an installation that will not only meet the standard warranty, but will provide an installation offering long-term reliability and minimum operating cost. Pump Management offer a complete service from conceptual design, supply, installation, commissioning and complete plant maintenance and operation throughout the life of the plant.
|

Pump System analysis of 2 pumps complete with 1.6MW drives
|

Stock feed pump at a major UK paper and board mill
|
|
Projects
- 2003 - Nuclear Power Station. Relocation of complete fire pump-house, pumps and system.
- 2004 - CCGT Power Station. Design, supply, install and maintain an abrasive estuary cooling water sludge transfer system, with a guaranteed minimum 500% reliability improvement.
- 2004 - CCGT Power Station. Design, supply and installation of mechanical seals, barrier fluid systems, power, control and instrumentation for main cooling water pumps.
- 2004 - Automotive Manufacturing Plant. Design, supply and install demineralised water system.
- 2005 - Pharmaceutical. Mechanical and electrical supply and installation of all pumps and control equipment.
- 2005 - Hydrocarbon. Civil, mechanical, electrical, instrumentation, process control and computer system for a major refinery fuel export pump and pipeline installation.
- 2005 - Automotive Manufacturing Plant. Up-grade coagulation recovery system.
- 2007 - Pharmaceutical. 60MW energy centre at major UK pharmaceutical company. Complete primary and secondary pump system design, supply and installation for high energy efficiency and sustainable low energy costs.
- 2007 - MoD. Complete design and build of 750kW primary and secondary cooling system for major MoD test facility.
- 2007 - Pharmaceutical. Design, supply and installation of 2 x 1MW absorption chiller system at major production facility.
Pump Management….engineered projects designed for optimum performance.
|
|
|
|
| |
© 2005 pump management limited
|
|
|